construction update lan handling

The realization of the new building for Lan Handling Technologies in Tilburg is going fast. The new business premises was designed by cepezed and cepezedinterieur and will house an assembly hall, engineering department and supporting office functions.

cepezedbouwteam, working in close collaboration with the architects of cepezed, is efficiently working on the entire construction coordination. The structural work is largely finished; for example, the entire concrete floor was poured and slashed last week. What remains are the assembly of the front façade and the overhead doors in the production hall. After new year, the installation of the M.E.P. installations takes place, followed by the implementation of the fixed interior. The accommodation by Lan is scheduled for spring 2019.